Deployment Plan
Schedule of Key Activities
Date | Activity | Responsible |
---|---|---|
Friday 5/23 |
| Ron |
 |
| Josh |
Monday 5/26 |
| n/a |
 |
| Tatenda |
Tuesday 5/27 |
| Josh |
Wednesday 5/28 |
| Sarah |
 |
| Tatenda / Josh |
Thursday 5/29 |
| Vidya |
 |
| Josh |
Friday 5/30 |
| Tatenda |
 |
| Rachel |
 |
| Tatenda |
Sunday 6/1 |
| Tatenda/Vidya |
 |
| Tatenda/Vidya |
 |
| Tatenda/Vidya |
Monday 6/2 to Tuesday 6/3 |
| Tatenda |
Â
Roles & Responsibilities Status Report
Â
Activity | Responsible | Due | Status | Issues/Blockers |
Overall Project Management | Sarah | n/a | GREEN | Â |
Scheduling Field Training | Aida | 5/19 | YELLOW | Need dates for Niassa and Cabo Delgado. Vidya to follow-up with Aida. |
Delivering Field Training | Tatenda | 6/2- 6/20 | GREEN | Â |
Process Knowledge Transfer | Vidya | Ongoing | GREEN | Â |
Refrigerator Inventory | Tatenda | 5/30 | YELLOW | Will not be done for all provinces in time for configuration. Backup plan is to pre-enter what is on provincial inventory then update (delete old entry, add new entry) once inventory is in. |
Software Development (Code Freeze) | Ron | 5/23 | DONE | On schedule. Ron to alert Josh when code is done. |
Tablet Field Trial | Tatenda | 6/3 | GREEN | Tablet field trial will start for July distribution. All three tablets are good to go. Tatenda to get movitel modems and adaptors and stabilizers. |
Training Materials | Vidya | 6/1 | YELLOW | Timeline is tight. Back from translator 5/30, must be to Maputo in final A4 format by 5/31 AM. Maputo team to print/bind/laminate by 5/31 in time for Monday's training. Â |
vrMIS Data Migration | Josh/Tatenda | 5/23 | YELLOW | March data is currently incomplete in vrMIS for Niassa and Gaza. Tatenda is working with the field coordinators to have them finalize the data entry by 5/28, then we will migrate the data. |
Final Deployment to SELV and SELV-Training | Josh | 5/26 | GREEN | SELV deployment complete. Selv-training will be deployed on Thursday. Â |
Final System Configuration (Products, Cachement Population, Users, Facilities) | Sarah | 5/28 | YELLOW | Waiting on facility list updates from Tatenda. Products, Users, and Cachement Population are done. Â |
Final Testing | Sarah | 5/30 | GREEN | Smoke Test Regression on changed features Validate configuratipon Exploratory Testing |
Reporting Distribution Process | Vidya (with planned transfer to Tatenda) | 6/15 | GREEN | Vidya to update SOP with location where files will be stored SELV-223 Vidya and Tatenda to confirm reports meet user needs during training SELV-263 |