UAT Entry Criteria - Status
UAT Entry Criteria Checklist
Key:
GREEN Already Done
YELLOW Expect to be completed for UAT starting 3/10
RED Not expected to be completed for UAT starting 3/10
Item | Status | Owner | Estimated Done Date (90% Confidence) | Notes |
---|---|---|---|---|
| DONE | Ron | 2/28 | |
| YELLOW | Timoteo | 3/10 | Timoteo at conference. Final showcase hasn't been reviewed. |
| DONE | Josh | Josh to work on lockdown. Offline access issue is impediment to UAT testing. Could start PC UAT before Tablet UAT. Lockdown moved to Go Live Entry | |
| YELLOW | Vidya & team | 3/7 | Separated Website UAT and Reporting UAT to mitigate the long delay in getting a response from Tableau on data source issue. Reporting UAT will start 3/19 |
| YELLOW | Vidya & team | 3/7 | Separated Website UAT and Reporting UAT to mitigate the long delay in getting a response from Tableau on data source issue. Reporting UAT will start 3/19 |
| GREEN | Josh | 3/7 | Almost complete. Need to validate no changes need for child coverage reporting. |
| GREEN | Josh | Need to migrate refrigerator inventory as well. (Josh & Ron to discuss) | |
| GREEN | Josh | 1/15 | |
| GREEN | Josh | 3/7 | SSL Cert still outstanding with Vendor - moving to production release. Logging issue resolved. Josh talked with Mike and now has access to the service issuing the certificate. Waiting for their verification process to complete. No time estimate currently. SSL moved out of scope.
|
| GREEN | Josh | 2/28 | |
| GREEN | Sarah | 3/7 | In progress. Will distribute to team for feedback (much needed!) |
| GREEN | Sarah, Vidya, Josh, Timoteo | 3/7 | Scope modified to include vrMIS data migration through Tableau. SELV Data Entry through tableau will be tested during UAT. |
| GREEN | Ron, Josh | 3/10 | On target for delivery by 3/10. |
Open Bugs Assigned to UAT Release