Date: Mar 06, 2014

Attendees

Objective

Get team up-to-date on project status and assess readiness to begin UAT on 3/10

Agenda

1. Project Status Update

...

 Completed Last Week

    • ThoughtWorks baseline stories release complete
    • Tablet selected, connectivity solution identified, & tablets purchased
    • Initial testing pass completed & bugs triaged (but some more to triage today)
    • Tableau workbooks tested and revised
    • ThoughtWorks team at work on SELV offline access bug
    • Team working in JIRA. Dashboards and releases created, along with significant Wiki content
 

...