11 Nov. 2016 - 23 Nov. 2016 (sprint ends the day before U.S. Thanksgiving holiday)
...
see /wiki/spaces/OP/pages/95289464
Velocity
Team ILL completed 29 story points. Teams AYIC/ToP completed 150 story points. If we continue this pace, the burn-up chart shows we will completed the story points for version 3.0 in time for a release in Sprint 19 (February 2017).
see Burn-up for 3.0 Release for details
Showcase
Video: OpenLMIS End of Sprint Showcase-20161123 1501-1.arf
The following 23 tickets were completed this sprint and covered at the showcase:
...
If sub-tasks are counted, there are 62 tickets representing 179 story points completed. View these issues in JIRA