Comment: Added Sprint 13 completed tickets, charts and showcase video

11 Nov. 2016 - 23 Nov. 2016 (sprint ends the day before U.S. Thanksgiving holiday)

...

see /wiki/spaces/OP/pages/95289464

Velocity

Team ILL completed 29 story points. Teams AYIC/ToP completed 150 story points. If we continue this pace, the burn-up chart shows we will completed the story points for version 3.0 in time for a release in Sprint 19 (February 2017).

Image AddedImage Added

see Burn-up for 3.0 Release for details

Showcase

Video: OpenLMIS End of Sprint Showcase-20161123 1501-1.arf

The following 23 tickets were completed this sprint and covered at the showcase:

...

If sub-tasks are counted, there are 62 tickets representing 179 story points completed. View these issues in JIRA