Date
Attendees
Goals
Discussion items
Time | Item | Who | Notes |
---|
| 3.5 Release Candidate test plan - Risk 1: When to schedule (Starts in Sprint 113)
- Still in discussion on when to start Release Candidate testing due to Zambia trip (Nov 26-30)
- Can we start regression testing and Malawi UAT with a smaller subset of team members during that week? Nov 26th
- Plan release candidate testing for a longer period of time?
- Status of test plan creation
- Reorganizing testing to focus on new features first, then regression testing
- Reviewing test cases created by other teams and adding them to the CoreRegression label OR has this been discussed in Tech Committee?
- Where do we expect to be with functional testing by the time we start release testing?
Tasks before Release Candidate testing starts: - Environments needed
- Need to let Josh know in advance how many environments we want to set up
- Who will own each environment? This needs to be listed in the test plan
- Resources
- Communication (before we start and during)
- Exploratory testing & Batch Approval testing
- Reviewing test cases from JSI before adding them to release candidate testing
Bugs that must be fixed before release candidate - Blocker and critical bugs
- Malawi bugs?
Setting up and managing bug triage - Core and Malawi should be included
- Monitoring Malawi UAT
| Sam Im (Deactivated) | Create different test cycles for each team that contain multiple components in each test cycle. |
|
|
|
|
Action items