2020-03-24 Sprint Transition

Date

Mar 24, 2020

Participants & Internal Stakeholders

  • @Felimone Amone Junior

  • @Matthew Kumbuyo (Deactivated)

  • @Chongsun Ahn (Unlicensed)

  • @Christine Lenihan

  • @Ben Leibert

  • @Sebastian Brudziński

  • @Aleksandra Ciesińska

  • @Mateusz Kwiatkowski

Retrospective

  • @Mateusz Kwiatkowski made good progress on the batch-approval work. @Aleksandra Ciesińska has primarily been focused on the Angola project, though provided critically important to support to @Felimone Amone Junior both before and during the UAT. The UAT went very well in large part thanks to @Aleksandra Ciesińska's support - thank you!


  • Working remotely has been a challenge for the team. Much of Soldevelo’s communication is via Slack and Google Hangouts. The problem is that eliciting feedback from a large number of people is slow. Scheduling a group-wide meeting for a quick question would be overkill, and the asynchronous nature of Slack means that it takes time for responses to trickle in.

Showcase

Planning

  • @Mateusz Kwiatkowski will focus on and the Batch-Approval tickets this sprint.


  • @Aleksandra Ciesińska will look into Angola’s requisition related reports - it’s unclear why most of them lack data. Although logging in with a user whom lacks the requisite rights to view requisitions could explain this, @Christine Lenihan has been using “admin3.”


  • Several other upcoming issues related to Angola may require @Aleksandra Ciesińska's time. To the degree that she’s available, though, she’ll focus on tickets in SELV’s prioritized ToDo column.