Backlog Grooming Sprint 40
Release Activities
Testing for RC3 was completed by Sam, Nick, and Josh (see RC3 Final Regression Testing cycle). RC3 is ready to be released on Thursday.
On Thursday Team Parrot will:
release all components (Services, UI, etc) EXCEPT openlmis-ref-distro. DO NOT RELEASE openlmis-ref-distro
As part of releasing each component, bump each service version to the next version
Update test.openlmis.org and contract tests to be deploying and testing the next SNAPSHOT versions (not the old RC or release)
Remember, do not change ref-distro (we, Team ILL, haven't finished the release notes)
Provide release status in #general
After 3.2.1 Release (only start these after components are released)
Goal: CCE final touches, reverted bugs, minor admin fixes, stock management Tech Debt.
CCE
Performance
https://openlmis.atlassian.net/browse/OLMIS-3493 (Team Parrot - this is an Epic, open it up and take these in priority order (OLMIS-3403 first and blocks others))
UI
Reference Data UI / Administration Screens
Stock Management
https://openlmis.atlassian.net/browse/OLMIS-3087 Q in ticket
https://openlmis.atlassian.net/browse/OLMIS-3167 (@Nikodem Graczewski (Unlicensed): we want you to re-start the discussion on the dev forum, ping @Josh Zamor (Deactivated) as needed, don't start coding anything yet for this)
had been in discussion, listed here to re-start it after v3.2.1 drops
Platform
Team ILL
Open Question: how do we 'see' into the reporting work and what dependencies exist? Do we know of dependencies?
https://openlmis.atlassian.net/browse/OLMIS-3423 (Ben doing for Malawi implementation)
https://openlmis.atlassian.net/browse/OLMIS-3585 (Josh has an email thread with Brandon and Elias)
https://openlmis.atlassian.net/browse/OLMIS-3583 (Rachel is writing ticket)
https://openlmis.atlassian.net/browse/OLMIS-3587 (Sam doing Product Committee research and proposal)
https://openlmis.atlassian.net/browse/OLMIS-3588 (MJ and Brandon) → connected to Reporting because it may need mock data
RTM
https://openlmis.atlassian.net/browse/OLMIS-3387 (first one in epic OLMIS-3385)
https://openlmis.atlassian.net/browse/OLMIS-3589 (Sam, Nick, Josh so the implementation could happen next sprint)
https://openlmis.atlassian.net/browse/OLMIS-3590 (Rachel leading ticket writing – Definition of Done is actionable tickets)
https://openlmis.atlassian.net/browse/OLMIS-3591 (Josh and Sam)
Reporting (Ona, MJ, Josh)
https://openlmis.atlassian.net/browse/OLMIS-3533 (Team ILL first needs to identify Desired Behavior)
https://openlmis.atlassian.net/browse/OLMIS-3505 (Related to OLMIS-3533) (Team ILL needs to review Desired Behavior for stock dates on emergency requisitions here)
@Nick Reid (Deactivated): FYI, UI stuff happening this sprint is Fulfillment and Making An Order stuff (see above).
WAIT------------------------------------------
Mobile Implementation
Mobile Strategy
Implementor Toolkit (Tenly involved after Thanksgiving)