2019-08-26 Meeting Notes
Participants
Agenda
Current Status
Present at upcoming Product Committee
Notes
Status:
Chongsun
Stood up instance of v3 reporting stack
Very little data for reporting stack to be useful
Progress is stuck on getting the test systems set up
Philip working on monitoring, proof of concept looks good
Josh
From meeting with Ashraf/Elias - Question about how much data needs to be moved over
Ian/Hassan
Working on NIDC integration
Setting up pipeline and v3
Test Instance Setup
Josh: These systems are intended to be setup on multiple machines. Standing up on a single server will require a power machine
Alfred: TZ team has been trying to set up everything on the same server (as this was all that was available)
Current setup:
16GB RAM, Lots 'o space, CPU?
Chongsun: Potentially possible to house elmis, pipeline, and v3 (not the reporting stack)
Next Steps
Setup v3 on a separate AWS instance (which account?)
NIDC
Josh: There is value in having v3 in the NIDC but it may not be worth having the whole pipeline in the national data center as this may slow things down
Install the pipeline and v3 in AWS. Move to NIDC as possible
Ian and Chongsun agree with this approach
Next Steps
Continuing to work through Casper epic tickets
Josh - proof of concept is wrapping up (nice!), now we're reading for the next phase
Need to figure out what that next phase would be and where the funding would come from
Need to show the poc working with the reporting stack
Alfred - Feedback from Ashraf/Elias to improve certain aspects of the workflow could be taken into account
Action Items
OpenLMIS: the global initiative for powerful LMIS software