2018-09-20 Configuration Improvements Discussion
Attendees
- Christine Lenihan
- Wesley Brown
- Mary Jo Kochendorfer (Deactivated)
- Sebastian Brudziński
- Sam Im (Deactivated)
Potential Improvements
- Finish the UI for all configurable elements
- Add missing pages/functionality
- Link related content to simplify configuration
- The UI for the various components should make it clear how the system is currently configured
- Use a tree of some sort to visualize Requisition Groups (etc)
- Include ability to see system as another user
- Wizard-based approach for common scenarios: - OLMIS-5120Getting issue details... STATUS
- Improve configuration documentation (Configuration Guide for Implementer/Administrator)
- Maybe move away from one giant page?
- Need to be able to generate a single page or pdf
- Clarify and simplify
- Additional visualizations
- Dependencies
- Maybe move away from one giant page?
- Built-in Configuration assistant:
-
OLMIS-5124Getting issue details...
STATUS
- Visualize the references between the entities.
- Simple display of what has/hasn't been loaded
- Simple configuration error checking
- Would be nice to be able to export/import products and facilities directly from olmis
- This would allow implementations to build the logic to do this in an automated fashion
- This used to be a feature but wasn't rebuilt in the re-architecture
- Christine highlighted that the error handling wasn't spectacular or helpful in understanding what is wrong with csv file (no real way to validate)
- Christine mentioned that csv export is very helpful to support the import
- Pick One Thing to Improve:
- Wes: Basic UI configuration for ALL THE THINGS
- Christine: Export of csv data for system configuration data
- Sebastian: Editing orderables via UI
- Currently a pain every week for Malawi
Discussion Points
What things are difficult??
- Sebastian
- Loading all the reference data is a challenge. Even with all the UI administration screens, you still won't be able to do it all through the UI and will use files (for example, products, facilities ALL of it!)
- Products and Facilities are the most difficult because (at least in part) of the amount of records and the relatively frequent changes
- So this is both an initial setup and ongoing difficulty
- Loading all the reference data is a challenge. Even with all the UI administration screens, you still won't be able to do it all through the UI and will use files (for example, products, facilities ALL of it!)
- Christine
- Challenge with Requisition Groups, difficult to grasp
- Difficult to set up using CSV
- Would like a wizard (some kind of UI to help visualize)
- Use the geographic levels and zones to create those requisition groups (very common that the those levels and zones fall in line of the requisition groups
- Validation that the setup is correct is currently very difficult
- Not a clear understand WHY a new requisition group is needed and when it is not (even though the first approval is the same, they still needed a new group because they wanted a second approval)
- Difficult to manage and validate user roles and role assignments
- Current design can lead to many roles that are all basically the same with minor variations
- Malawi currently has "hundreds" of role assignments (facility and program combination), this is difficult to maintain
- Setting up testing/training was a lot of work
- Cannot have multiple people logged in as the same user
- Have to create many users and data set
- Even if the system supported same-user login, difficulties with individual Requisitions and working over each other
- Sam: We have similar problems in our core testing
- Set up distinct environments to be able to test concurrently
- Sebastian: This didn't work
- Because of shared services (I think)
- Have only 1 person testing each component in each environment
- Cannot have multiple people logged in as the same user
- Challenge with Requisition Groups, difficult to grasp
Action Items
- Sebastian Brudziński Find the Requisition Groups graph visualization that he liked to the group: https://openlmis.atlassian.net/secure/attachment/18359/requisition%20group_facilities_supervisory%20diagram.png
- Wesley Brown To schedule follow up with Sam Im (Deactivated) regarding UI for all components