2018-09-14 Team Lead Meeting notes
Date
Sep 14, 2018
Attendees
@Sebastian Brudziński
@Sam Im (Deactivated)
@Wesley Brown
Discussion Points
3.5 Release will be at the end of 111 so much (all?) of that sprint will be spent in the QA/Release process
Sam: Concerned about multiple supplier feature in that time frame
Still scoping feature
May need to add people to get done in time
Reminder: explain tickets before demonstrating in the showcase
Reminder: update sprint goals on backlog grooming & JIRA sprint boards
Periodic Regression Testing
MtG currently evaluating tests to remove old/unuseful tests
Currently expected to do this every other sprint - not sure if this is realistic
QA Team handles this for all teams
Sam to discuss this on Monday
Sam would like to schedule a 3.5 scope discussion with Mary Jo and Josh, would this be helpful for anyone else to join?
Is everyone clear on their team's scope for 3.5?
Sebastian: Helpful to discuss what parts of release improvement will be completed for 3.5
Mind the Gap (Sam):
See question below about OLMIS-4886 and OLMIS-5302
Having retrospective 107 later today
Discussing spikes for mCSD
Couple of spikes for mCSD that team is working on now
Gathering requirements for multiple supplier feature
Fast Parrot (Sebastian):
What is/will be the outcome from https://openlmis.atlassian.net/browse/OLMIS-4886 and how does this compare to https://openlmis.atlassian.net/browse/OLMIS-5302?
OLMIS-5302 Deaded
Setting Tests to Dead when not needed or handled by contract tests
Updating tests to make sure they are still current
Priority is SBR (OLMIS-5395)
Still working on remaining columns but easy work
Total cost is not calculating correctly
Approved qty is not defaulting correctly
Primary focus is on release faster, working on overall strategy with CCE service
Also working on a few bugs and tech debt
Ona (Craig/Clay): Not present
JSI (Ashraf): Not present
Action items
@Wesley Brown Get firm date for 3.5 release, which sprint will be the last before the release