2018-09-14 Team Lead Meeting notes
2018-09-14 Team Lead Meeting notes
Date
Attendees
Discussion Points
- 3.5 Release will be at the end of 111 so much (all?) of that sprint will be spent in the QA/Release process
- Sam: Concerned about multiple supplier feature in that time frame
- Still scoping feature
- May need to add people to get done in time
- Sam: Concerned about multiple supplier feature in that time frame
- Reminder: explain tickets before demonstrating in the showcase
- Reminder: update sprint goals on backlog grooming & JIRA sprint boards
- Periodic Regression Testing
- MtG currently evaluating tests to remove old/unuseful tests
- Currently expected to do this every other sprint - not sure if this is realistic
- QA Team handles this for all teams
- Sam to discuss this on Monday
- Sam would like to schedule a 3.5 scope discussion with Mary Jo and Josh, would this be helpful for anyone else to join?
- Is everyone clear on their team's scope for 3.5?
- Sebastian: Helpful to discuss what parts of release improvement will be completed for 3.5
- Is everyone clear on their team's scope for 3.5?
Mind the Gap (Sam):
- See question below about OLMIS-4886 and OLMIS-5302
- Having retrospective 107 later today
- Discussing spikes for mCSD
- Couple of spikes for mCSD that team is working on now
- Gathering requirements for multiple supplier feature
Fast Parrot (Sebastian):
- What is/will be the outcome from
-
OLMIS-4886Getting issue details...
STATUS
and how does this compare to
-
OLMIS-5302Getting issue details...
STATUS
?
- OLMIS-5302 Deaded
- Setting Tests to Dead when not needed or handled by contract tests
- Updating tests to make sure they are still current
- Priority is SBR (OLMIS-5395)
- Still working on remaining columns but easy work
- Total cost is not calculating correctly
- Approved qty is not defaulting correctly
- Primary focus is on release faster, working on overall strategy with CCE service
- Also working on a few bugs and tech debt
Ona (Craig/Clay): Not present
JSI (Ashraf): Not present
Action items
- Wesley Brown Get firm date for 3.5 release, which sprint will be the last before the release
- The release will be at the end of Sprint 111
- Wesley Brown Follow up with Craig/Clay and Ashraf regarding reminders
- Wesley Brown Follow up with Ashraf about 3.5 scoping meeting
- Discuss how to better introduce and give context to the work that each team is doing during the showcase